Robert's Rules states that business can come before an assembly by a motion or by the presentation of a communication to the assembly. At our last meeting we had a presentation, and we would like to open it up again for additional discussion and public comment. Is it proper to place this under "unfinished business" even though no action was taken on the presentation and there are no unresolved motions?
Placing a Prior Presentation Under Unfinished Business
The short answer is: No, this would not properly come under "Unfinished Business."
Why "Unfinished Business" Doesn't Apply Here
Unfinished business has a specific, technical meaning under Robert's Rules. It consists of:
- Business postponed to the current meeting (via Postpone Definitely)
- Business that was pending when the previous meeting adjourned (a motion that was interrupted)
- General orders (matters scheduled for the current meeting)
Robert's Rules makes clear that unfinished business is not simply "anything we discussed before." Since no motion was pending and no action was taken, there is nothing left "unfinished" in the parliamentary sense.
The Proper Way to Bring This Back
Since this is essentially new business, the correct approach is to:
- Place it under "New Business" on the agenda
- Have a member make a main motion regarding the subject — for example:
- "I move that the assembly receive additional public comment on the presentation"
- "I move to refer this matter to a committee for further review"
- Or any other substantive motion arising from the presentation
Without a motion, there is no parliamentary basis for discussion, because Robert's Rules establishes that debate must be tied to a pending motion.
A Practical Note
If your assembly simply wants an open discussion without taking formal action, you might consider:
- A motion to suspend the rules to allow general discussion
- Or, if your bylaws permit it, scheduling it as a program item outside of the formal business meeting
Key Takeaway
Labeling something "unfinished business" when it doesn't meet that definition is a procedural error that could be challenged via a Point of Order. Placing it properly under New Business with an accompanying motion is the correct path forward.